Extension of Project End date with all tasks extended

Sebastian Fernandez De Soto 0 Reputation points
2026-01-05T12:08:13.2433333+00:00

I currently have a project with a fixed end date of March 9
I need to extend the Project to the end of June 9 - I have already put the final task as ending on June 9
I need all tasks to extend their duration to match the new end date - essentially we have more time for all tasks

Do I need to extend all tasks manually or is there a way to do it quick whil3e respecting all precedents?